#P3553. Task schedule

    ID: 2563 远端评测题 2000ms 64MiB 尝试: 0 已通过: 0 难度: (无) 上传者: 标签>Northeastern Europe 2003, Western Subregion

Task schedule

Description

There are n preemptive jobs to be processed on a single machine. Each job j has a processing time pj and deadline dj. Preemptive constrains are specified by oriented graph without cycles. Arc (i,j) in this graph means that job i has to be processed before job j. A solution is specified by a sequence of the jobs. For any solution the completion time Cj is easily determined.

The objective is to find the optimal solution in order to minimize

max{Cj-dj, 0}.

Input

The first line contains a single integer n, 1 ≤ n ≤ 50000. Each of the next n lines contains two integers pj and dj, 0 ≤ pj ≤ 1000, 0 ≤ dj ≤ 1000000, separated by one or more spaces. Line n+2 contains an integer m (number of arcs), 0 ≤ m ≤ 10*n. Each of the next m lines contains two integers i and j, 1 ≤ i, j ≤ n.

Output

Each of the n lines contains integer i (number of job in the optimal sequence).

2
4 1
4 0
1
1 2
1
2

Source

Northeastern Europe 2003, Western Subregion